A new Natatorium will be constructed to replace the current aquatic center. This facility will feature twenty 25-meter lanes, a diving well with boards and spectator seating.

Design Process
Construction Process
Longview High School, E Tomlinson Pkwy, Longview, TX 75605, USA
Budget
$41,900,000
New Construction
35,000 SF
Renovations
N/A
Construction Starts
Q2 2026
Anticipated Opening
Q2 2027
Trustee
Mr. Brett Miller

Project Team

Paul Miller
Owner’s Representative
Contractor
CDI Contractors LLC
Architect
DLR Group

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
03/02/2026
Mobilization is in progress by CDI Contractors in preparation for the start of clearing and grading.
02/18/2026
The DLR Group design team held a visioning meeting with the School District to discuss options for new furniture, fixture and equipment selections for the new CTE addition, the new Multi-Purpose Facility and the new Natatorium.
02/09/2026
The Board of Trustees approved CDI Contractors’ Guarantee Maximum Price for construction.
02/02/2026
The DLR Group has completed the 100% Construction Drawings. Permits are in progress.
09/19/2025
75% Construction Documents (CDs) Drawings have been received for the Natatorium Project
09/19/2025
The New Natatorium Project: Draft Renderings