Multi-Purpose Indoor Facility

Key Information

A new Multi-Purpose Indoor Facility will be constructed with a 120-yard turf field for marching band and sports, batting cages, golf simulation, a weight room, locker rooms and coaches’ offices.

Design Process
Construction Process
Longview High School, E Tomlinson Pkwy, Longview, TX, USA
Budget
$48,000,000
New Construction
112,000 SF
Renovations
N/A
Construction Starts
October 2025
Anticipated Opening
Q4 2027
Trustee
Mr. Brett Miller

Project Team

Paul Miller
Owner’s Representative
Contractor
SCI Construction
Architect
DLR Group

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
07/14/2026
Progress Update!

Progress continues at the Multi‑Purpose Indoor Facility as SCI advances earthwork, utility installation, and foundation preparation. Heavy equipment remains active across the site, shaping the building pad and establishing essential early infrastructure that will support upcoming construction activities.

04/07/2026
The Foundation of Something Great

SCI Construction has placed the foundation at Area A.3. Work is continuing with grade beam installation at Area A.2, which will be the next area prepared for foundation placement.

03/02/2026
Grade Beam Installation

Work continues with the installation of grade beams as SCI Construction prepares to place the foundation at the first area.

02/18/2026
Visioning & FF&E Discussions

The DLR Group design team held a visioning session with the School District to review options for new furniture, fixture, and equipment selections for the CTE addition, the Multi‑Purpose Facility, and the Natatorium.

02/13/2026
New Multi-Purpose Indoor Facility

SCI Construction continues with drilled piers and utilities.

01/16/2026
New Multi-Purpose Indoor Facility

SCI Construction is hard at work continuing with the completion of site work and the underground utilities.

01/09/2026
New Multi-Purpose Indoor Facility: Sitework continue
12/11/2025
New Multi-Purpose Indoor Facility: Sitework has begun
09/17/2025
100% Construction Documents (CDs) Drawings for the New Multi-Purpose- Received and submitted to the City of Longview
09/17/2025
New Multi-Purpose Indoor Facility: DRAFT Renderings – Exterior

The DLR Group has issued DRAFT renderings of the exterior.