Natatorium

Key Information

A new Natatorium will be constructed to replace the current aquatic center. This facility will feature twenty 25-meter lanes, a diving well with boards and spectator seating.

Design Process
Construction Process
Longview High School, E Tomlinson Pkwy, Longview, TX 75605, USA
Budget
$41,900,000
New Construction
35,000 SF
Renovations
N/A
Construction Starts
February 2026
Anticipated Opening
Q4 2027
Trustee
Mr. Brett Miller

Project Team

Paul Miller
Owner’s Representative
Contractor
CDI Contractors LLC
Architect
DLR Group

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
07/14/2026
The Pool Is Beginning to Take Form!

Site and foundation work continues to progress positively. Concrete walls and below‑grade structural elements are now in place, outlining the natatorium’s footprint. CDI is actively backfilling, grading, and preparing the area as the project builds momentum for upcoming construction activities.

03/31/2026
Grading in Full Swing!

CDI Contractors continues grading the site as preparations move forward for upcoming construction activities.

03/02/2026
Ready to Roll! Mobilization Begins

Mobilization is underway as CDI Contractors prepare the site for the start of clearing and grading.

02/18/2026
Visioning & FF&E Discussions

The DLR Group design team held a visioning session with the School District to review options for new furniture, fixture, and equipment selections for the CTE addition, the Multi‑Purpose Facility, and the Natatorium.

02/09/2026
The Board of Trustees Approved CDI Contractors’ Guarantee Maximum Price for Construction.
02/02/2026
The DLR Group has completed the 100% Construction Drawings. Permits are in progress.
09/19/2025
75% Construction Documents (CDs) Drawings have been received for the Natatorium Project
09/19/2025
The New Natatorium Project: Draft Renderings