Transportation Center

Key Information

The new Transportation Center addition expands the current Center, this addresses the lack of much needed space.

Design Process
Construction Process
1111 East Young Street, Longview, TX, USA
Budget
$7,800,000
New Construction
10,000 SF
Renovations
N/A
Construction Starts
Q3 2026
Anticipated Opening
Q3 2027
Trustee
Ms. Lateefah Pruitt

Project Team

Paul Miller
Owner’s Representative
Contractor
Jackson Construction
Architect
DLR Group

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
04/07/2026
Transportation Center: The DLR Group has completed the Design Development/50% Contract Documents phase. The 100% Contract Documents phase is now underway with completion tentatively scheduled for June 2026.
02/02/2026
The DLR Group has completed the Schematic Design (SD) Phase and are now in the Design Development (DD) Phase.
09/19/2025
The DLR Group has been selected to continue as the Architect for the new Transportation Center Project