The new Career and Technical Education Center will be constructed to modernize school infrastructure and enhance learning environments by increasing career and technical programs.

Design Process
Construction Process
Longview High School, E Tomlinson Pkwy, Longview, TX, USA
Budget
$59,000,000
New Construction
95,000 SF
Renovations
N/A
Construction Starts
October 2025
Anticipated Opening
Q3 2027
Trustee
Mr. Brett Miller

Project Team

Paul Miller
Owner’s Representative
Contractor
SCI Construction
Architect
DLR Group

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
08/20/2026
Building Momentum

Crews have begun installing exterior sheathing across the CTE Center’s steel frame. With panels going up section by section, what was just structural steel a few weeks ago now reads unmistakably as a building.

07/14/2026
Vertical Construction is Underway!

Vertical construction has been progressing steadily for the past month, with steel framing and concrete wall sections now fully defining the building’s shape. Crews remain active across the structure each week, keeping momentum strong as the project continues to rise.

04/07/2026
Foundation Progress

SCI Construction has placed the foundation at Areas A.1, A.2, and B.1. Work continues with the installation of grade beams at Area B.6, which will be the next location for foundation placement.

03/02/2026
Foundation & Structural Progress

The foundation has been placed at the first area, completing this phase of work. Installation of grade beams is now underway at the next area as SCI Construction advances into the following phase of construction.

02/18/2026
Visioning & FF&E Discussions

The DLR Group design team held a visioning meeting with the School District to discuss options for new furniture, fixture and equipment selections for the new CTE addition, the new Multi-Purpose Facility and the new Natatorium.

02/13/2026
New Career & Technology Education Center

SCI Construction continues with drilled piers, pier caps and beam walls.

01/16/2026
New Career & Technology Education Center: SCI Construction is hard at work continuing with the completion of site work and the underground utilities.
01/09/2026
New Career & Technology Education Center: Sitework continue
12/11/2025
New Career & Technology Education Center: Sitework has begun
09/17/2025
100% Construction Documents (CDs)- Drawings for the CTE Addition Project- Received and submitted to the City of Longview