Career & Technology Education Center

Key Information

The new Career and Technical Education Center will be constructed to modernize school infrastructure and enhance learning environments by increasing career and technical programs.

Design Process
Construction Process
Longview High School, E Tomlinson Pkwy, Longview, TX, USA
Budget
$59,000,000
New Construction
95,000 SF
Renovations
N/A
Construction Starts
October 2025
Anticipated Opening
Q3 2027
Trustee
Mr. Brett Miller

Project Team

Paul Miller
Owner’s Representative
Contractor
SCI Construction
Architect
DLR Group

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
04/07/2026
Career and Technical Education Center Addition Project: SCI Construction has placed the foundation at Area A.1, Area A.2 and Area B.1. Work continues with the installation of grade beams at Area B.6, this will be the next area for foundation placement.
03/02/2026
The foundation has been placed at the first area completing this phase, work continues with the installation of grade beams at the next area as SCI Construction enters the next phase.
02/18/2026
The DLR Group design team held a visioning meeting with the School District to discuss options for new furniture, fixture and equipment selections for the new CTE addition, the new Multi-Purpose Facility and the new Natatorium.
02/13/2026
New Career & Technology Education Center: SCI Construction continues with drilled piers, pier caps and beam walls.
01/16/2026
New Career & Technology Education Center: SCI Construction is hard at work continuing with the completion of site work and the underground utilities.
01/09/2026
New Career & Technology Education Center: Sitework continue
12/11/2025
New Career & Technology Education Center: Sitework has begun
09/17/2025
100% Construction Documents (CDs)- Drawings for the CTE Addition Project- Received and submitted to the City of Longview
09/17/2025
New Career & Technology Education Center: DRAFT Renderings – Exterior

The DLR Group has issued DRAFT renderings of the exterior.

09/17/2025
New Career & Technology Education Center: SCI Construction completed its Pre-Bid Meeting